3 field photosUnsuitable subgrade at west loading dock
Hawthorne Commerce Center — Dock Apron Replacement · Summit Peak Builders
Soft material continued below the planned 4-inch cut at the west dock. Mark asked us to remove it, haul it off, and rebuild the base before we pour. Approx. 180 SF, average 6 inches additional depth.



Remove and dispose of unsuitable subgrade discovered below the planned excavation at the west loading dock. Rebuild the affected area with compacted Class A base material to support the scheduled concrete placement. Price includes crew labor, skid-steer time, base material, haul-off, and disposal for the approximately 180-square-foot area shown in the attached photos.
Price covers conditions and quantities shown. Additional unsuitable material outside the marked area will be documented separately.
Confirm dump ticket is attached to the project folder. Protect Friday concrete slot if approval lands today.
- Extra work documented
Unsuitable material found below the planned cut at the west loading dock.
Eli Martinez - Sent to office for pricing
Field report, requester, schedule impact, and three photos included.