RedbudFieldChange
Cut-out concrete loading dock apron with the soft subgrade area marked in orange 3 field photos
Needs PricingWork blocked
FC-1048 · HC-2407

Unsuitable subgrade at west loading dock

Hawthorne Commerce Center — Dock Apron Replacement · Summit Peak Builders

Customer amountNot pricedOffice action required
Handoff pathPricing
Captured2Pricing3Approval4Completion5Billing
$Next: price the field changeTurn Eli’s field report into a customer-ready scope and amount.
Price Change
Soft material continued below the planned 4-inch cut at the west dock. Mark asked us to remove it, haul it off, and rebuild the base before we pour. Approx. 180 SF, average 6 inches additional depth.
Estimated quantityApprox. 180 SF; 6 in. additional depth
Requested byMark EllisonSummit Peak Builders
Schedule calloutAdds one working day to Redbud's dock-apron scope.
Cut-out concrete loading dock apron with the soft subgrade area marked in orange
West dock cut-out; soft area marked in orange.
Close view of wet subgrade with a grade rod showing additional excavation depth
Additional depth below plan, approximately 6 in.
Skid steer and dump trailer along the west drive haul-off route
Access and haul-off route from west drive.
Edit in pricing →

Remove and dispose of unsuitable subgrade discovered below the planned excavation at the west loading dock. Rebuild the affected area with compacted Class A base material to support the scheduled concrete placement. Price includes crew labor, skid-steer time, base material, haul-off, and disposal for the approximately 180-square-foot area shown in the attached photos.

PriceNot priced
Schedule impactAdds one working day to Redbud's dock-apron scope.
Assumption

Price covers conditions and quantities shown. Additional unsuitable material outside the marked area will be documented separately.

Internal costs, margin, and this note never appear in the customer view or approval payload.

Confirm dump ticket is attached to the project folder. Protect Friday concrete slot if approval lands today.

  1. Extra work documented

    Unsuitable material found below the planned cut at the west loading dock.

    Eli Martinez
  2. Sent to office for pricing

    Field report, requester, schedule impact, and three photos included.

    Eli Martinez